City contract vendors / Who gets the city's money

Walsh Construction Company II, LLC. — City of Chicago contracts

Every contract the City of Chicago has on file with this vendor: what was awarded, which departments issued it, and how the awards were procured. Figures are computed live from the city's official contracts dataset.

Recorded in city contract data as WALSH CONSTRUCTION COMPANY II, LLC..

$1,002,911,814

Total awarded

Net of revisions and de-obligations

1,127

Contracts on file

Earliest approved Nov 17, 2011

$159,439,294

Largest single award

Jun 30, 2026

Most recent approval

A note on the totals: the city files revisions and de-obligations as their own records with negative award amounts, so the total above is the net of awards and adjustments. An awarded amount is also not money paid — it is the ceiling the city agreed to, and actual spending can come in lower.

Departments, by total awarded

  1. Ohare Modernization Project$517,894,360
  2. Chicago Department Of Transportation$228,342,937
  3. Chicago Department Of Aviation$194,546,977
  4. Department Of Water Management$34,817,132
  5. O'hare Modernization Program$27,310,409

Largest individual contracts

  1. OMP Runway 9R-27L Extension - East, ORD(Spec 1190708) — 2020$159,439,294
  2. MIDWAY INTERNATIONAL AIRPORT TERMINAL PARKING GARAGE EXPANSION (SPEC #406900) — 2018$143,081,000
  3. OMP Runway 9C-27C Bid Pkg #3 & RWY 4L-22R Rehab (Spec 862852) — 2019$94,983,087
  4. OMP Runway 9C-27C East Package - ORD, Spec 163099 — 2016$69,849,082
  5. TERMINAL 5 M CONCOURSE EXTENSION SITE/CIVIL PACKAGE (SPEC #766477) — 2019$64,073,360
  6. THE BLOOMINGDALE MULTI-PURPOSE TRAIL AND PARK - CONTRACT 1 — 2013$53,738,952
  7. TAXIWAY Z/J AND TANK FARM ROAD — 2017$52,794,635
  8. CHICAGO RIVERWALK - LASALLE STREET TO LAKE STREET — 2015$52,419,384

How the work was procured

  1. BID1,018 contracts

Contract types

  1. CONSTRUCTION-AVIATION781 contracts
  2. CONSTRUCTION-LARGE $3MILLIONorABOVE346 contracts

Walsh Construction Company II, LLC. contracts most heavily with Ohare Modernization Project, which accounts for $517,894,360 across 553 contract records.

Walsh Construction Company II, LLC. contracts FAQ

How much has Chicago awarded to Walsh Construction Company II, LLC.?
City of Chicago contract records show $1,002,911,814 awarded to Walsh Construction Company II, LLC. across 1,127 contract records approved since Nov 17, 2011. That figure is the net of awards and later adjustments, and an award is not the same as money actually paid out.
Which city departments contract with Walsh Construction Company II, LLC.?
By total award amount, the departments contracting with Walsh Construction Company II, LLC. are: Ohare Modernization Project ($517,894,360); Chicago Department Of Transportation ($228,342,937); Chicago Department Of Aviation ($194,546,977); Department Of Water Management ($34,817,132); O'hare Modernization Program ($27,310,409).
What is the largest Walsh Construction Company II, LLC. contract?
The largest single award on file is $159,439,294, described by the city as "OMP Runway 9R-27L Extension - East, ORD(Spec 1190708)", approved May 6, 2020, through Ohare Modernization Project.
Why can a contract amount be negative?
The city records revisions and de-obligations as separate rows with negative award amounts. That means a vendor total is the net of original awards plus every later adjustment, not a running tally of payments. Awarded dollars are also not the same as dollars spent — a contract can be awarded and only partly drawn down.

Source

Contracts are matched on the vendor name exactly as the city records it, so a company filed under more than one spelling may appear on more than one page. Award amounts can be negative on revisions and de-obligations; totals are the net of awards and adjustments, not payments made.